Over three decades, CONCO has been involved in the design, supply, installation and commissioning of high voltage substations and overhead lines. Along the way, our skilled directors, loyal shareholders and talented employees have maximised their many years of experience and multi-layered knowledge to revolutionise Africa’s electrical system capabilities – via successful turnkey engineering projects.
For insight into the proven track record that has earned CONCO an enviable reputation in the industry, please feel free to explore our wide range of projects in more detail.
| Group Projects 6-10 | 11-15 | 16-20 | 21-25 | 26-30 | 31-35 of 58 |
Segoditshane 220/132 kV Substation (Botswana) |
09-11-2009 |
Segoditshane 220/132 kV Substation and 125 MVA Transformer |
|
|
|
|
Nseke Overhead Line Project (Democratic Republic Congo) |
09-10-2009 |
This project consisted of the rehabilitation and the strengthening of the southern DRC’s power network. A double circuit line was built to reinforce the power network of the Tenke-Fungurume Mining, while in Kolwezi the project consisted of stringing a 220 kV line on existing towers and refurbishing the existing lines. New towers were also built in Kolwezi to accommodate the changes made to the network. |
|
|
|
|
Auas - Naruchas Transmission Line (Namibia) |
20-10-2009 |
Turnkey Construction of Auas to Naruchas 132 kV Transmission Line |
|
|
|
|
Tenke Fungurume 220 kV Supply (Democratic Republic Congo) |
23-07-2009 |
Tenke Fungurume 220 kV Supply |
|
|
|
|
Tarkwa Gold Mine (Ghana) |
22-07-2009 |
Supply, installation, erection, testing and commissioning of 161 kV and 11 kV equipment for Tarkwa Substation as well as for New Tarkwa Substation in Ghana |
|
|
|
|